| Project Name: Douglas Byrd Middle School |
Date Completed: September 2010
|
| Contract Amount: $2.8 Million |
Project Type: Educational
|
| Location: Fayetteville, NC |
|

Douglas Byrd Middle
School project scope consisted of replacing the existing gymnasium
building that was destroyed by fire. The kitchen and locker rooms
received extensive smoke damage and were completely renovated with
all new finishes as part of the scope. One of the major obstacles
involved remediating the smoke present in the locker room. The
kitchen area was replaced with all new food service equipment. The
second phase of the project included a 6-classroom addition. All
work was completed on time and within budget.
|